A roof replacement is a short job with a long run-up. The on-roof work on an average house takes one to three days; the inspection, decisions, insurance, permit and scheduling that come before it take weeks. Knowing the sequence lets you plan around it and recognise when something is out of order.
Stage 1: Inspection and proposal (days 1–7)
A roofer inspects the roof and attic, documents it with photos, and produces a written proposal listing materials, scope, price, schedule and terms. Get two or three for a replacement. This stage is where most of the decisions get made: shingle grade and ratings, tear-off vs. overlay, flashing, ventilation, decking allowance. The roof replacement page explains each line; questions to ask covers the rest.
Stage 2: Insurance, if the roof is a claim (days 3–30+)
For storm claims, the adjuster’s inspection, the insurer’s estimate and any supplement negotiation happen here, and they set the pace. Have the roofer present for the adjuster’s visit and agree the scope before signing a contract. Expect the insurer to pay in two parts if your policy is replacement-cost: an initial actual-cash-value payment and the recoverable depreciation after the work is completed and invoiced. See the insurance claim guide.
Stage 3: Contract, permit and materials (days 7–21)
- Sign the contract with scope, schedule, payment terms and warranties in writing. Deposit practices vary; Colorado restricts deposits on insurance-related jobs.
- The contractor applies for the permit. Many cities issue re-roof permits the same day or within a few days (see the permit guide); historic-district reviews take longer.
- Materials are ordered. Common shingle colours are usually in stock; designer products, metal panels and tile can take weeks.
- Scheduling depends on the crew’s backlog and the weather forecast; after large storms, backlogs stretch for months.
Stage 4: The day before
- Materials and a dumpster are delivered to the driveway; move vehicles to the street.
- Take pictures and fragile items off walls and shelves; the vibration is real.
- Cover items in the attic with plastic; tear-off drops dust and debris through gaps in the deck.
- Mark sprinkler heads, low-voltage lighting and plants you want protected; agree where ladders and the debris chute will go.
- Plan for pets and children to be away from the work area.
Stage 5: Tear-off and deck repair (day 1)
Crews strip the old covering and underlayment to the deck, usually starting early. Rotten or soft decking is identified and replaced; this is when the per-sheet decking price applies and when you should be reachable for decisions. The crew installs drip edge, ice-and-water membrane at eaves and valleys, and underlayment the same day so the house is never left open overnight. If weather turns, the roof is tarped at this stage.
Stage 6: Dry-in inspection (where required)
Florida and some other jurisdictions inspect the underlayment, flashing and deck nailing before the covering goes on. The contractor schedules it; the crew may pause for it. Elsewhere, the first inspection is the final one.
Stage 7: Flashing, covering and ventilation (days 1–3)
New step, counter, valley and pipe flashing go in as the covering is installed from the eaves up. Ridge vents are cut in, ridge caps installed, and ventilation balanced. Tile, metal, steep or complex roofs take longer: tile and standing seam can run a week or more on a large house.
Stage 8: Cleanup, walkthrough and final inspection
- Magnetic nail sweeps of lawn, beds and driveway; debris and dumpster removed.
- Walk the property with the foreman: look at flashing, ridge, edges, gutters, siding and any damage to landscaping; check the attic for daylight and debris.
- The city’s final inspection; keep the record.
- Final invoice listing what was done, decking sheets used, and the workmanship warranty; manufacturer warranty registered in your name.
- For insurance jobs, send the final invoice to the insurer to release recoverable depreciation.
What stretches the timeline
| Cause | Typical effect |
|---|---|
| Post-storm demand | Weeks to months of backlog; insurance adjusters also delayed |
| Weather | Rain and high wind stop work; crews reschedule around forecasts |
| Material availability | Specialty shingles, metal and tile lead times |
| Historic-district or HOA review | Days to weeks before a permit or approval |
| Hidden deck damage | Extra hours to a day, and a change order |
| Insurance supplements | Negotiation can pause the start if the contractor waits for approval |
Common questions
Do I need to be home during the replacement?
Not all day, but be reachable for decking decisions and be there for the final walkthrough.
Can the crew leave the roof open overnight?
They should not. Tear-off and dry-in happen the same day, and the roof is tarped if weather interrupts.
When do I pay?
Per the contract: commonly a deposit when materials are delivered and the balance on completion and inspection. Avoid paying in full before the final walkthrough.